Building Projects We’re Monitoring

9038 Reading (ED1 100% Affordable)

Published Date: 20 - NOV - 2024

#1: BaBWP's TAKE

As ED1 projects go, this is a respectable build project and we’re pleased to see this number of new affordable units coming to market in Westchester.  

The Location

The Reading-Ramsgate neighborhood is very attractive to for-profit developers seeking to enter the ED1 game. There are multiple ED1 projects in the Planning pipeline for the area, which has long served as one of our community’s historically multi-family areas.

The Developer

This project’s developer is Tommy Beadel (founder of Thomas James Homes). He has a track record of mastering new market opportunities.

It’s clear from ED1 Planning applications filed by Tommy Beadel he and his team are working a formula. They understand ED1 Planning application requirements, and they’re getting projects approved all over Los Angeles with relatively quick turn-around.

Tommy Beadel buildings don’t deliver show-stopping architecture or amenities—but this is to be expected,  constrained as they are to hit financial performance targets in a 100%-affordable build. (In our observation, for-profit affordable developers typically don’t provide the same level of design or on-site amenities provided by non-profit 100%-affordable developers.)

Published Date: 20 - NOV - 2024

#2: PLANNING FILE #(s)

Published Date: 15-DEC-2024

#3: WHO'S INVOLVED

Owner/Developer 

 

Land Use Consultant

Published Date: 15-DEC-2024

#4: PROJECT OVERVIEW

Building type: ED1 100% Affordable

 

# Residential Units

  • 77 units

 

Timing

  • Application filed: 10-31-2024 
  • Application approved: Pending
  • Construction Start Date: Unknown
  • Construction Completion Date: Unknown
  • Occupancy Date: Unknown

 

Other Specs (taken from Planning files, developer docs, etc.)

Planning Application Description: “Demolition of existing buildings and construction of 77 unit 100% affordable apartment building 5 stories tall and 55 feet in height.”

 
Incentives + Waivers Granted:
  • 55′ height (5 stories)
  • Other details not available as of this posting on LA Planning Case Summary system.

Published Date: 15 - DEC - 2024

#5: RENDERING & PLANS

Published Date: 15-DEC-2024

#6: WHAT THIS PROJECT IS REPLACING

Published Date: 15-DEC-2024

#7: CITY APPROVAL & CONDITIONS LETTER

Pending.