Building Projects We’re Monitoring

8615 Ramsgate (ED1 100% Affordable)

Published Date: 07 - Feb - 2025

BaBWP's TAKE

On their website, Modulyft  promotes other projects demonstrating the modular-build approach in LA.

Looking more closely at their website’s promotion of  “8615 Ramsgate – Phase 1” it appears the group is still fundraising for the project. However, given the modular approach to the building’s design, when the funds are in place, this project is likely to go up faster than the traditional “stick-build” approach, due to Off-site construction, then craning pieces into place.

(See BaBWP “take” below and our guess this project would take a while to break ground because the original applicant—Anthony Gude—did not appear to be well capitalized.) 

Further, it does appears the project’s ED1 application with Planning has not moved off it’s “On Hold” status.

Therefore, it’s conceivable ground-breaking on this project is still some time out, as devlopers fundraise.  

What we still don’t know yet: The target affordable income brackets the building intends to target. 

We also are watching a general ED1 new-build trend around the Reading & Ramsgate area. Given the neighborhood’s location (close to the Veteran’s Metro train station) and the zero-parking requirement of State law for 100% affordable buildings, we can expect highly concentrated densification in this area. 

As of today (7-Feb-25) these are the  ED1 100% affordable high-density projects slated for this neighborhood: 

Published Date: 07 - Feb - 2025

PROJECT INFORMATION UPDATES

Owner/Developer Update

  • Today UrbanizeLA reported that this project developer is no longer Anthony Gude alone. 
  • (Note: the Planning Case file online does not reflect this change.)
  • Developer now identified by UrbanizeLA as Modulyft
  • Anthony Gude  is now a partner at Modulyft, rather than the sole developer.
 

Other UrbanizeLA story details: 

  • Architect: Peter Demaria of Mid-Rise Modular 
  • Proposing 8 stories
  • 72 studio and 1 bedroom units rather than the original Planning Application file figure of 82 units.

 

Land Use Consultant

  • None listed in Planning application.

Published Date: 07 - Feb - 2025

RENDERING & PLANS

Published today in UrbanizeLA.  

Published Date: 07 - Feb - 2025

RENDERING & PLANS

Found on developer’s website (Modulyft).  

Published Date: 15-Dec-2024

BaBWP's TAKE

Case on HOLD per Planning file summary (see case file link below ). 

In response to a BaBWP.org email checking on this application status, the assigned planner Esther Serrato replied via email on 11-19-2024 “The case has been placed on hold due to a number of missing filing materials. Once those materials are provided then case processing may proceed.”  

She also indicated the case file is available for review by scheduling an appointment with Records Management @ 213-847-3753 or emailing [email protected].

Regarding the Developer 

Per BaBWP.org’s research, it seems Anthony Gude has been involved funding capture for the modular multi-family construction trend. For example, in an interview he refers to fundraising for a Multifamily Industrialized Construction & Development Fund. 

It is our impression that Gude does not currently have a large portfolio of ED1 projects or applications. One indication: lack of a corporate website. A second indication: the project’s incomplete initial Planning application.

Currently there are larger developers working successfully to get ED1 applications proposed and approved. One example: Tommy Beadel of HVN, who has three ED1 projects active in the Reading-Ramsgate area. Per Beadel’s project elevations, it’s pretty clear his firm has the ED1 formula down and they’re rolling out many ED1 projects throughout Los Angeles. 

Therefore, it’s possible 8615 Ramsgate will proceed more slowly, given the developer’s smaller size and relative lack of ED1 development experience. 

Published Date: 15-Dec-2024

PLANNING FILE #(s)

Published Date: 15-DEC-2024

WHO'S INVOLVED

Owner/Developer 

 

Land Use Consultant

  • None listed in Planning application.

Published Date: 15-DEC-2024

PROJECT OVERVIEW

Building type: ED1 100% Affordable

# Residential Units

  • 82 units

Timing

  • Application filed: 4-17-2024 
  • Application assigned on 7-18-2024 to Esther Serrato
  • Application placed on hold (no date given)
  • Application status: Pending
  • Construction Start Date: Unknown
  • Construction Completion Date: Unknown
  • Occupancy Date: Unknown

 

Other Specs (taken from Planning files, developer docs, etc.)

Planning Application Description:  PROPOSED (N) 82-UNIT 100% AFFORDABLE HOUSING APARTMENT BUILDING.

Incentives + Waivers Granted:
  • Details TBD (waiting further info from Planning)

Published Date: 15-DEC-2024

WHAT THIS PROJECT IS REPLACING

Published Date: 15-DEC-2024

CITY APPROVAL & CONDITIONS LETTER

Per Planning Case look-up system, this application is on hold.